Saxwerk has signed an agreement with SCA Gällö Timber to supply a 15 MW Power Plant for hot water to their wood dryers

2017-05-23T18:25:47+02:002017-02-06|

The delivery is a turnkey contract with fuel handling, furnace, boiler and electrostatic precipitator. Delivery includes boiler house and outsourced pipe construction. The mechanical installation begins after the summer. Commissioning will take place in early 2018. If you have questions about this article, please contact Tomas Wendt, phone: +46 8-500 666 95. [...]